Construction Progress
October/ November 2009 update
For previous reports see Construction Progress Archive.
Mollinsburn Link Overbridge
Pier construction completed at the Mollinsburn Link Overbridge. This structure will carry the new Westfield Link Road over the M80, improving access to the industrial estate.
Mollinsburn Overbridge
HMC have completed piling works to the Mollinsburn Overbridge. When completed this structure will provide access from the Gartferry Rd to Mollinsburn over the new extended section of the M73.
Luggie Water Underbridge
HMC successfully completed the installation of precast concrete beams for the Luggie Water Underbridge. This bridge structure across the Luggie Water forms part of the new Westfield Link Rd.
M73/M80 Link Overbridge

Ongoing construction of the reinforced concrete leaf piers at the M73/M80 Link Overbridge. This structure will carry northbound traffic from the M73 over the new M80.